Construction & Commissioning
Facility construction and commissioning; initial production capacity of 3,000 t/y online.
Months 0–6 — Site development and construction; core utilities installed.
Months 6–12 — Pilot and preliminary production; initial fiber output and product validation.
Months 12–24 — Main industrial commissioning; ramping toward 3,000 t/y.